The overall objective was to assist the Montenegrin administration in the implementation of the Instrument for Pre-Accession Assistance (IPA), in the preparation of investment projects and improvement of mechanism for an effective EU accession process.
Main task was the preparation of projects in the Water Supply, Wastewater, Waste, Nature and Flood Protection Sectors, by means of e.g. field studies, feasibility studies, designs, cost benefit analysis, environmental impact assessments, tender documentation in line with the Montenegrin Law on Planning and Construction and EU best practices.
Project Director: Mr Lars Lauridsen
Key Experts Team Leader: Mr Peter Blaschke
Procurement Expert: Mr Srdjan Topalovic
Kick-off date: 18 February 2021
Duration: 36 months (original); 47 months (amended)
Closing date: 17 January 2024 (original); 21 December 2024 (amended)
Budget: EUR 3,234,000.00 (original); EUR 4,378,890.00 (amended)
The Contract between the Montenegrin Public Works Administration (later on named Capital Projects Administration) and the JV COWI A/S (Denmark) and CeS.TRA (Serbia) for the Project Preparation Facility (PPF) was signed on 16/12/20 for a value of EUR 3,234,000. The team was mobilised on 18/01/21 and a kick-off meeting was held in Podgorica with MERT (previous MESPU) on 21/02/21. The original completion date was 17 January 2024.
The Contract was extended in the course of Contract Addendum #06 in May 2024 to a value of EUR 4,378,890 and completion date to be 21 December 2024.
In total 33 Sub-Project and SPASS were completed, all in the WS, WW, SW and NAT sector as well in Capacity Building in these sectors – all aiming to support MNE in achievement of Chapter 27 objectives. Beside the previous, some SPASS (Small Project Advisory Support Service) were initiated, however for numerous reasons not completed.
Summarised, the following was elaborated/ delivered/ conducted: